Management Tool: Arrow Diagram BrainKart
To complete the project at 20 hours, it is essential that one reaches event 14 by 18 hours. In this way . we get the time by which the events must be accomplished. These are given in table 4. Applications . The most common application of an arrow diagram is in planning and scheduling projects which involve a large number of activities. The